  • Replacement of chains, buckets and rails of old D.B.C no 1 and 2 and erection of same in stipulated time.
  • Replacement of tip casting of kiln no 2 in record time of 7 hours.
  • Erection and commissioning of fly ash handling System and its complete piping.
  • Replacement of G.C.T ( Gas Conditioning Tower no 2) shell, cone and duct at upto 70 mtr height with app. Wt. 85 MT including H.P piping with dismantling and Erection of new within record time of 13 days.